Latest news
A recommendation has been made for the planning corridor
Following an assessment of several variants, a proposal has been put forward for the future planning corridor of the new 220-kV line between Bickigen and Mettlen. Swissgrid will plan the specific route of the line at a later stage within this geographical area, which is approximately 400 to 2,400 metres wide.
The recommendation was drawn up by a support group led by the Swiss Federal Office of Energy (SFOE). Technical, ecological, economic and regional planning aspects were weighed up carefully against one another.
The recommended corridor consists of an overhead line. It mainly follows existing infrastructure areas, thereby helping to minimise any further alterations to the landscape and environment. At the same time, it lays the foundations for a route that is more compatible with residential areas than that of the current line.
The municipalities of Neuenkirch and Rothenburg in particular stand to benefit in the long term from the dismantling of the existing line, which will reduce the impact on numerous residential areas.
The recommended planning corridor
The recommended planning corridor consists of an overhead line and begins at the Bickigen substation in the municipality of Wynigen. Like the current line, it runs south past Huttwil to the Willisau substation. From there, the corridor continues south of Neuenkirch and north of Rothenburg towards the Mettlen substation in the municipality of Eschenbach. This provides an opportunity to optimise the route of the line compared with the current situation and reduce the impact on the affected residential areas even more.
The public can express their views
Before the Federal Council makes a decision on the planning corridor, members of the public, municipalities, organisations and other interested parties will have a chance to have their say as part of the official consultation and participation procedure.
The project documents are expected to be available for public inspection in the affected municipalities for a period of 30 days starting from the end of November.
All the feedback submitted will be examined by the Swiss Federal Office of Energy and may lead to modifications to the corridor recommendation. In conjunction with the project documents, the results of the consultation will form the basis for the Federal Council's decision.
Public information events
Swissgrid is organising public information events in collaboration with the SFOE and the participating cantons. Find out more about the project and put your questions directly to the project team:
- Monday, 2 November 2026, 7.00 p.m.: Turnhalle, Gymnasium, Kappelenstrasse 25, 3472 Wynigen
- Wednesday, 4 November 2026, 7.00 p.m.: Multi-purpose school hall, Schulhausstrasse 2, 6203 Sempach Station
Next steps
The support group's corridor recommendation will be subject to the official consultation procedure with the authorities and the public. The Federal Council is expected to define the corridor, and therefore also choose the technology for the new line, by mid-2027. Swissgrid will then establish the specific construction project and submit the planning approval application to the competent authority, the Swiss Federal Inspectorate for Heavy Current Installations (ESTI). This will be followed by a public consultation on the construction project.
The following schedule is based on the current planning status and represents the best possible scenario, without taking into account potential legal proceedings.
Project
Swissgrid operates Switzerland's 6,700-kilometre extra-high-voltage grid, ensuring that electricity reaches where it is needed safely, efficiently and in an environmentally responsible manner at all times. A strong and modern grid is essential to ensure a reliable electricity supply for Switzerland in the future.
The 220-kilovolt line between the substations in Bickigen (municipality of Wynigen, canton of Bern) and Mettlen (municipality of Eschenbach, canton of Lucerne), which is 53 kilometres long, is the oldest line in the Swiss transmission grid. It was built in 1928 as a 132-kV line and upgraded in 1951 for operation at 220 kilovolts. Now the line needs to be replaced. This was shown by a comprehensive survey, during which all 178 electricity pylons and their concrete foundations, insulators and conductors were analysed and documented.
Swissgrid will replace the 220-kV Bickigen – Mettlen line in two stages:
- Short-term renovation of the existing line: Short-term renovation measures will ensure operation for the next 15 to 20 years. The insulators, conductors and fittings on the existing 220-kV line will be replaced on a one-to-one basis. The landscape will not be altered. This work is expected to take place between February and October 2026.
- Long-term line replacement: The long-term plan is to replace the existing line with a new 220-kV line; the voltage will not be increased. The planning and implementation will be carried out as part of a sectoral plan procedure (Transmission Lines sectoral plan, SÜL) and will include an evaluation of the relocation of the line.
The sectoral plan procedure for the long-term replacement of the line
At the end of March 2025, Swissgrid submitted an application to the Swiss Federal Office of Energy to initiate the sectoral plan procedure. The Transmission Lines sectoral plan (SÜL) is the Swiss government’s superordinate planning and coordination tool for the construction and expansion of transmission lines. The SÜL procedure consists of two steps:
- Step 1: Planning areas are first drawn up, i.e. geographic areas in which the new line should be built. The planning area is defined by the Federal Council.
- Step 2: In the application made to initiate the sectoral plan procedure, Swissgrid made a recommendation for possible working corridor variants within the defined planning area. The transmission technology is always already determined for each corridor, i.e. it has been decided whether to plan the line as an overhead line, an underground cable or a combination of the two technologies.
The planning territory
In the Bickigen – Mettlen project, there was insufficient scope for several planning areas. Swissgrid therefore developed a single proposal for the planning area in consultation with the participating cantons of Bern and Lucerne. The planning area takes into account technical, ecological and regional planning factors. The aim was to avoid sensitive areas but to include all the necessary connection points.
Within the planning area, Swissgrid worked out possible corridor variants for the route of the new line. These working corridors are geographical areas of a width of around 400 to 2,000 metres. They show where the line could run in the future. A support group led by the Swiss Federal Office of Energy (SFOE) will decide which option will be pursued and submitted to the Federal Council for approval as part of the official sectoral plan procedure. The municipalities and the local population can also comment on the project and voice their concerns. All the details of the sectoral plan procedure can be found here.
The working corridors
Swissgrid has divided the planning area for the new 220-kV line into three sections. Possible corridors have been developed for each section, which will now be examined and discussed with a support group as part of the sectoral plan procedure. The aim is to find the best possible route for the new line.
Close connection to the Innertkirchen – Mettlen project
As part of the SÜL for the Bickigen – Mettlen project, the routing of the 380-kV Innertkirchen – Mettlen line on the section between Mettlen and Hellbühl (Littau) is also being reviewed. This is because the Innertkirchen – Mettlen and Bickigen – Mettlen lines to the west of Rothenburg run closer and closer together. From Rothenburg onwards, they are bundled on two parallel routes as far as Mettlen.
Why underground cables should only be used selectively
Laying new underground cables in the Swiss transmission grid only remains possible to a very limited extent. This is the result of the Swissgrid cable study, which shows that the physical properties of underground cables make stable grid operation and the rectification of disturbances much more difficult. An uncontrolled increase in the proportion of underground cables in the extra-high-voltage grid would have a negative impact on Switzerland’s security of supply. For future grid projects, the possibility of installing an underground cable should therefore be considered from an overall perspective.
Dismantling of the old line
The project will reduce the impact on residential areas – in the municipalities of Rothenburg and Neuenkirch in particular, there will be a significant improvement on the current situation. The plan is to install the new line as far away as possible from residential areas. The existing line will be completely dismantled once the new 220-kilovolt line has been commissioned.