en

Grid project Mörel – Ulrichen

A new 380 kilovolt line is being constructed between Mörel and Ulrichen. The construction of this line is necessary to ensure that all of the energy generated from hydropower in the Valais can reach Central Switzerland and Ticino.

Your contact for this grid project

Jan Schenk

Overview

The extra-high-voltage line between Mörel and Ulrichen will be newly constructed with a voltage of 380 kilovolt. Without connecting the transmission lines in the Valais to the 380-kilovolt grid, it will only be possible to transport around two thirds of the Valais production from hydropower once the new Nant de Drance pumped storage power plant commences operation. The construction of the SBB's new 132 kilovolt railway power line is also critical for the secure operation of the New Railway Link through the Alps (NRLA) at the Gotthard.

Improvement compared to the current situation

Opinions and impressions of the project
Opinions and impressions of the project

Project

Bitsch/Massaboden – Mörel section

Mörel – Ernen section

Schedule for the sub-section between Mörel-Filet and Ernen

Construction of access paths H2 2020 – H1 2021
Clearing Q3 2020 – Q2 2021
Construction of foundation Q1 2021 – Q4 2022
Installation of pylons Q4 2021 – Q2 2023
Fitting of conductors Q2 2023 – Q4 2024
Protection against corrosion Q2 – Q3 2025
Commissioning Q4 2028*
Dismantling of 220 kV and 65 kV lines Q2 – Q4 2029
Recultivation 2022 – 2030
* The new 380/65-kV line can only go into operation once the new 65-kV Ernen substation is ready for commissioning.

Ernen – Ulrichen section

57 new pylons were built and the existing 220 kilovolt and 65 kilovolt overhead lines will be dismantled between the Ernen and Ulrichen substations. The main work (foundation and pylon construction, rope installation) took place between 2017 and 2020.

The total costs for the new Mörel – Ulrichen extra-high-voltage line amount to approximately 110 million Swiss francs.

General site plan Ernen – Ulrichen section

Dismantling

The existing 220-kilovolt overhead line between Mörel and Ulrichen will be taken down after the new line has been commissioned. The existing 65-kilovolt Mörel – Ernen 1, Mörel – Ernen 2 and Ernen – Ulrichen overhead lines will also be dismantled.

Pylons, conductors, ground conductor and insulators

Steel lattice pylons and plastic insulators will be used for all pylons.

1,000 mm2 Aldrey conductors are used for the transmission and railway power lines; twin conductors will be used in the transmission line. The 65-kilovolt line will be equipped with 600 mm2 Aldrey single conductors. The ground conductor has a diameter of approx. 350 mm2 and contains an integrated fibre-optic cable.

Ernen substation

A modern 220-kilovolt substation is being built at the new location in Niederernen. The old substation in Fiesch and the line connection will be dismantled. This will avoid crossing the Rhone and relieve the burden on the residential area. The centrepiece of the new 220-kV Ernen substation is the gas-insulated switchgear. A second 220/65-kV transformer will also be installed to increase regional security of supply. Valgrid and its partners GKW and KWRB are building a new 65-kV substation at the Niederernen site.

According to the current project planning, it will not be possible to commission the new Ernen substation until the end of 2028 at the earliest. Until Valgrid is ready to operate the Ernen substation, GKW and Valgrid will remain reliant on the Fiesch substation and the connection via the existing line.

Meinungen und Eindrücke vom Projekt
Time lapse: New construction of the operations building at the Ernen substation

Mörel substation

Swissgrid is reinforcing the substation in Mörel to increase security of supply. Firstly, a 380-kV gas-insulated switchgear is being built in Mörel. This will replace an ageing outdoor switchgear system. Swissgrid is also installing a new 380/220-kV transformer. The existing 220-kV switchgear is being extended. Swissgrid is also installing a new 380/220-kV transformer. The conversion work is scheduled to begin in 2027 with the construction of the transport routes and the replacement of the 380/220-kV transformer station in the Mörel substation. This is dependent on the approval process. Commissioning is dependent on the progress of the Chippis – Mörel and Mörel – Ulrichen 380-kV line projects

Cable study Binna crossing

General site plan cable study Binna crossing
General site plan cable study Binna crossing

A bridge solution to the Binna crossing is being considered for cable version 1. The cable bridge is a version in the topologically difficult area of the Binna crossing with steep drops on both sides.

The cable bridge could be used as a pedestrian connection. Special consideration must be given to the magnetic field on account of the proximity of the pedestrians to the cable arrangement. An aluminium panel could be attached above the cable arrangement to shield the magnetic fields.

Visualisierung Binnaquerung
Visualisation of the Binna crossing cable
Video: Extra-high voltage line in Goms – construction work between Mörel-Filet and Ernen completed

People & environment

Electromagnetic fields

A total of 19 buildings within the study perimeter were classified as OMEN. The magnetic field was calculated for all OMENs. In 18 OMENs, the system limit value of 1 microtesla was maintained. In one OMEN, the system limit was exceeded slightly – a dispensation has been granted for this.

Landscape

The new line routing is used in the entire project perimeter south of the existing building zones and residential areas. By moving the line from the banks of the Rhône and out of the open agricultural land to the wooded hillsides, the potential conflict of the existing 220 kV line from the construction zones in several communities will be resolved. In terms of the landscape, there will be a general improvement over the existing situation.

Due to the bundling with the 132 kV railway power line and the 65 kV line on the same pylons as well as to the higher voltage, however, the pylons will be taller than the existing 220 kV line.

Forests

The majority of the pylon sites are located in the forest. Other locations are used intensively for agriculture or include semi-dry meadows and extensively grazed areas.

Along the Ernen – Ulrichen section, the clearing work along the line route was carried out in the spring of 2018. This was necessary to ensure safety on the construction site and safe operation of the line. An approximately 30-metre-wide corridor was cleared over a distance of around 16 kilometres. Trees and shrubs are beginning to grow again in this area. Over time, this will allow the line to blend into the landscape better.

A total forested area of 15,288 m2 had to be cleared to install the line at the pylon locations along the Ernen – Ulrichen section. The temporary clearing of 22,572 m2 is required to provide access to the building sites and pylon locations. Suppression is necessary for an area of 292,471 m2.

Grid project Mörel – Ulrichen: Forest-clearing

Planting of silver fir trees

The forests in Goms consist mainly of spruce and larch trees. Due to climate change, damage caused by the bark beetle is occurring more and more frequently in these forests. This is jeopardising the spruce population and the important protective function that the forests offer against avalanches. Open patches are increasingly appearing in-between trees, putting additional pressure on the larch population. The Swiss Federal Research Institute WSL is placing a growing focus on the local silver fir as a climate-resistant species. Silver fir trees will be planted in selected areas in Goms from next spring and, where necessary, will be protected against browsing by wild animals. The planting and maintenance will be carried out by a local forestry company. This will guarantee the protective function of the forest areas in the long term.

Aufwuchs von Weisstannen
Planting of silver fir trees

Natural hazards

After every forest-clearing measure, Swissgrid checks whether additional safety measures are required to protect people and the environment. For example, snow barriers and timber tripods are erected to protect against avalanches. Moreover, Swissgrid also plants young trees in glades along the line route. These kinds of precautions were taken in the municipalities of Ernen, Goms and Obergoms. They guarantee the safety of the roads, which are used year-round, during winter. Besides this, they also support the growth of the forest in the vicinity of the line. The measures allow the forest to fulfil its long-term role of unrestrictedly protecting against avalanches.

In the section stretching from Mörel to Ernen, the forest-clearing activities along the line route are expected to be carried out by the spring of 2021. In this section Swissgrid will once again review whether additional protective measures for avalanches and snow slides are necessary. A definitive assessment of the situation and the agreement upon suitable measures is possible only after deforestation.

Protecting alpine meadows from overgrowth

The construction of the extra-high voltage line will have an impact on nature. By way of compensation, Swissgrid will implement various renaturation projects in the affected municipalities between Mörel-Filet and Ulrichen. For instance, on the Tunetschalp, Swissgrid has created a wet habitat while also contractually assuring that the Tunetschalp and Gorneralp will be regularly maintained over the next 20 years to protect against overgrowth.

As another compensation measure, Swissgrid also intends to protect dry meadows and pastures from overgrowth. A total of seven meadows and pastures will be cleared of overgrowth between Ulrichen and Ernen alone. The associated activities started in autumn 2019 and will last until the end of 2021. The overgrowth in these areas will continue to be managed in the future in order to preserve their ecological value.


Downloads


Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.