Electricity is always flowing and the energy sector is always active – 24/7, 365 days a year. New grid projects, exciting facts about electricity, digitalisation, innovations, the environment – we regularly publish informative articles on a wide range of topics. Always up-to-date, always with our finger on the pulse. Welcome to our blog!
«Price signals are probably the strongest argument.»
Electricity no longer seems to be available as a matter of course. We need to change our behaviour in order to utilise this resource in a more sustainable way. A conversation with Dr Christian Berger, research associate at the University of Bern’s Institute for Organisation and Human Resource Management (IOP).
The grid must always be taken into account when installing a solar plant
Large solar plants are to be built in the Swiss mountains by as early as 2025. This represents a challenge for grid operators: they have to implement the grid connections.
The Swissgrid substation at Fionnay GD in the Valais, which is located in a mountain cave, has been renovated. This is where the energy generated by the Fionnay / Grande Dixence power plant is fed into the electricity transmission system.
The expansion of domestic production capacity is essential in order to ensure a successful energy transition in Switzerland and to strengthen security of supply in the long term. This became even clearer in the light of the supply situation in the winter of 2022/2023.
Power shortage and power system failure are two terms that are often confused. But they do not mean the same thing. In the event of a power system failure, there is enough energy in the system in principle. However, a chain of unfortunate circumstances leads to a power failure. In a power shortage, on the other hand, production capacity is insufficient to meet demand.
The assembly of the cable connection gantry for the La Bâtiaz – Le Verney underground link and the replacement of pylon 51 on the Chamoson – Romanel 380 kV overhead line are under way at the Verney construction site in Martigny. These two elements are essential for connecting the underground link to the Swiss extra-high-voltage grid. The underground cable link is scheduled to be commissioned in spring 2022.
In the new brochure “Substations and Transformers – Important Elements in the Transmission Grid”, we describe the role of switchgear and transformers in the transmission grid in simplified terms.
Cable laying for the underground link between La Bâtiaz and Le Verney in Martigny is currently under way. Delivery of the twelve cable reels has been taking place in stages since the beginning of December, as the cables need to be warmed up before being installed in the gallery. The underground cable link is scheduled to be commissioned at the end of March 2022.
Without interrupting the transmission of electricity
Since 5 November 2021, the electricity produced by the hydroelectric power plant in Fionnay in Valais has been transported via Swissgrid’s 220 kV Fionnay–Riddes overhead line.