Grid project Bassecourt – Mühleberg

The enhancement of the Bassecourt – Mühleberg extra-high-voltage line is part of the «Strategic Grid 2025». Swissgrid needs the 380-kV connection between Bassecourt and Mühleberg to ensure the security of supply in the medium-term. This is particularly important in the winter months, when Switzerland relies on additional energy imports.

Your contact for this grid project

Jan Schenk
Jan Schenk

Phone +41 58 580 21 11
info@swissgrid.ch

380 kV line
380 kV line
Existing line
Existing line
Substation
Substation

Overview

The decommissioning of the Mühleberg nuclear power plant will result in the removal of part of Swiss energy production in Central Switzerland from the end of 2019. In the medium-term, this missing feed-in needs to be offset by higher production by Swiss power plants or energy imports from abroad. To enable the additional imports, the existing capacities of the extra-high-voltage lines and transformers between Bassecourt and Mühleberg need to be expanded. This is particularly important in the winter months, when Switzerland relies on additional energy imports.

In a normal supply situation, Greater Bern will receive an adequate supply of electricity even after the decommissioning of the Mühleberg nuclear power plant. In the event of short-term grid congestion, the Swissgrid grid control room can take various measures, such as switching operations or interventions in electricity generation (redispatch) or measures on the power market (NTC adjustments), to respond to the situation and ensure grid stability. Swissgrid needs the 380-kV connection between Bassecourt and Mühleberg to ensure the security of supply in the medium term.


Project

The Bassecourt – Mühleberg extra-high-voltage line is 45 kilometres long and was built in 1978. The Federal Inspectorate for Heavy Current Installations (ESTI) approved the line for an operating voltage of 380 kV back in 1978. However, it has been operated with a voltage of only 220 kV since that time. The voltage increase will take place in compliance with the limits specified in the Ordinance on Protection against Non-Ionising Radiation (NISV).

The line will be modernised along the existing pylons and will not change the landscape. Construction work is planned on 54 of a total of 142 pylons: individual pylon foundations will be reinforced, double anchor chains will be installed, or the cable winch tension will be increased. The future operation at 380 kilovolts will result in an increase in noise emissions that will be hardly noticeable.

The planned construction measures to increase the voltage of the Bassecourt – Mühleberg line can be technically implemented in a short period of time (approx. 12 months).

The construction costs for the increase in voltage and modernisation of the Bassecourt – Mühleberg extra-high-voltage line amount to approximately 11 million Swiss francs.

Schedule

On 22 August 2019 the Swiss Federal Office of Energy approved the voltage increase of the extra-high-voltage line between Bassecourt and Mühleberg from 220 to 380 kilovolts and dismissed the objections. These generally related to the load from magnetic fields and the noise or demanded that the line route be relocated or cabled. Various appellants have appealed to the Federal Supreme Court against the decision made by the Swiss Federal Office of Energy. The Federal Supreme Court confirmed the planning approval for increasing the voltage of the Bassecourt–Mühleberg line, rejecting all complaints, on 23 March 2021.
The planned construction measures for the voltage increase are expected to start in 2022 and last around one year. Swissgrid is planning to put the new 380 kV line into operation in the automn of 2023.

30 June 2017 Start of the planning approval procedure
22 August 2019 SFOE planning approval decision
15 September 2020 Decision by the Federal Administrative Court
23 March 2021 Decision by the Federal Supreme Court
2021/2022 Invitations to tender
2022 Construction and civil engineering / pylon and cable assembly
Autumn 2023 Commissioning

Substations

New transformers in the Mühleberg and Bassecourt substations

Swissgrid has commissioned a new transformer in the Mühleberg substation. Together with the increase in voltage of the extra-high-voltage line, the transformer in Mühleberg will ensure that current can be transported with a voltage of 380 kV as well as 220 kV.

The last of four transformer poles was delivered to Mühleberg in mid-September 2020. The new transformer was transported from the port Auhafen in Basel to Mühleberg in four heavy-load transporter trips. Every transformer pole has a transport weight of 170 tons and is around 11 metres long, almost 3.6 metres wide and 4.5 metres high. The transformer will be ready for operation from the end of 2020.

The renovation work for the new 380/220 kV phase-shifting transformer in the Bassecourt substation has been completed. The new transformer has been in operation since May 2020 and enables better control of the energy flows from France.

1/2: The transformer pole is lifted and placed on the rails.
2/2: The transformer pole is drawn into the chamber with the help of a pulley system.
A giant comes to Mühleberg (video in German)

People & environment

Noise

  • The increase in voltage in a transmission line from an operation at 220 kV to 380 kV results in an increase in the maximum electrical field strength of the overhead line, which results in an increase in the noise level on the line.
  • The planning figures, i.e. the most stringent statutory precautionary values in accordance with the Noise-Protection Ordinance (LSV), are complied with at all noise-sensitive areas operating at 380 kV.
  • The existing quadruple conductor is currently already reducing the noise level along the line. The precautionary principle specified by the Noise-Protection Ordinance is therefore largely taken into account.
  • The noises are caused by the corona effect, which primarily occurs during wet weather conditions (rain, snow, fog). The noises are barely perceptible in fine and dry weather.

Electromagnetic fields

  • Magnetic fields
    • The emission limit for a magnetic field of 100 microtesla is complied with in all places where people may be present.
    • The optimum phasing is determined for the different sections in the project. The phase difference is already optimised in the section between Mühleberg and Pieterlen. The phase difference will be optimised for the section between Pieterlen and Bassecourt, which will result in an improvement from the current condition.
  • Electric field: The increase in voltage to 380 kV will also lead to an increase in the line's electric field. The emission limit (IGW) of 5 kV/m is complied with at all points.

Downloads


Project news

  • | Media release

    Bassecourt – Mühleberg voltage increase

    Read article
  • | Blog

    A giant comes to Mühleberg

    Read article
  • | Blog

    Mühleberg goes offline

    Read article

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.