en

Grid technologies

Overhead line or cable?

Overhead lines and underground cables

At extra-high-voltage level (380 kV and 220 kV), electricity is currently predominantly transported using overhead lines. They account for 99 percent of the Swiss transmission grid. The use of underground cables in the extra-high-voltage grid is comparatively new, and experience in the field is relatively limited. Both technologies have their advantages and disadvantages with regard to project planning, construction, operation and maintenance. That is why Swissgrid examines the overhead line and cabling options for every grid project.

Overhead lines

Swissgrid maintains 12,000 pylons in the extra-high-voltage grid throughout Switzerland. Many of them are located in challenging terrain: in mountainous, steep locations that are often difficult to access, on rocky, sometimes unstable ground. Building new lines on this type of terrain poses technical difficulties. To do so, Swissgrid can draw on a wealth of experience and technical expertise.

Underground cabling

As opposed to overhead lines, underground cabling has rarely been used at the highest voltage level in Switzerland until now. This is because its use is only possible under certain conditions. A number of critical factors, such as soil conditions, transmission capacity, route length, costs and line capacity utilisation need to be taken into account. Swissgrid laid extra-high-voltage cables for a 380-kilovolt line in the ground for the first time in 2019, thereby collecting important findings and data for the future.

Construction methods for line projects

Overhead line construction: stable foundations

1/3: The pylon of an extra-high-voltage line requires a maximum area of 15×15 metres. Its foundation is built solidly: it must not only support the pylon, but also ensure that it does not tip over in strong winds. Depending on the height of the pylon and the terrain – especially in the mountains, where pylons are often located on steep or unstable terrain – additional safety measures may be necessary. Structural measures such as metal nets or concrete reinforcements protect the pylons from avalanches, rockfalls or falling debris.
2/3: The electricity pylon constantly grows upwards during the installation work. For most pylon sites on steep terrain, helicopters transport the individual pylon elements from the installation sites to the pylon sites. For other pylons, the pylon parts are lifted up piece by piece using an assembly tower.
3/3: Once the pylon has been built, the conductors that will later transmit the electricity are attached to the insulators. First, a helicopter is used to suspend the preliminary cable. This is made of nylon to keep the weight as low as possible for aerial assembly work. The next step is to pull much heavier steel cables up along the preliminary cables. Then the conductors which will later transmit the electricity are installed.

Route construction: how a cable is laid in the ground

How are transmission lines laid underground? Which methods are suitable for which terrain – and how do they affect construction time, costs or load-bearing capacity? When planning lines, Swissgrid always looks for the best possible way to reconcile the four areas of economic efficiency, technology, spatial development and the environment. The «Lines construction kit» is an important tool for finding solutions. It gives a precise description of the advantages and disadvantages of the various possible solutions whilst addressing the need to carefully weigh up all the construction options.

Video «Gäbihübel» (in German)

Visible elements of underground cabling

Protecting the landscape is a major advantage of underground cabling. A large part of the line infrastructure is hidden in the ground. However, underground cables also leave traces in the landscape, for instance in the form of aisles in forests, access roads and transitional structures that connect overhead lines to the underground cables. Special shaft constructions are used to inspect and repair the cable connections. The voltage is stabilised with compensation systems. Other visible signs of underground cabling include access roads and forest aisles.

Detailed information on behaviour near lines

Maintenance and operation

Overhead lines and underground cables have advantages and disadvantages when it comes to operating and maintaining the grid. Technical challenges such as ensuring voltage stability increase as the number of underground cable sections of the transmission grid rises. This is because the two technologies have different electrical properties, which have an impact on the stability and availability of the transmission grid.

Costs

The construction costs of an extra-high-voltage line can vary a great deal from case to case – depending on the topography, subsoil, potential natural hazards and technology. As a general rule, a kilometre of underground cable in the transmission system is around two to ten times more expensive than a kilometre of overhead line. When assessing economic efficiency, Swissgrid takes into account not only the construction costs, but also the life cycle costs of the various line variants.

Swissgrid’s calculation is based on a line service life of 80 years. However, various components must be replaced sooner. In the case of underground cables, the underground cables themselves are a particularly important cost factor. Due to their technical life expectancy, underground cables can only be operated for half as long as overhead lines and have to be replaced completely after around 40 years.

Cost of overhead lines

1/3: Chamoson – Chippis 4.7 CHF million per km – The extra-high-voltage line between Chamoson and Chippis carries four voltage levels on the same pylon: 380 kV, 220 kV and 65 kV between Chamoson and Aproz, and 132 kV SBB between Chamoson and St-Léonard, allowing almost 89 kilometres of lines to be dismantled on the Rhône plain.
2/3: Airolo – Lavorgo CHF 3.6 million per km – The new 380-kV extra-high-voltage line between Airolo and Lavorgo runs along the right-hand side of the valley and replaces the existing 220-kV line. A 132-kV SBB line is bundled on the same pylons to supply the AlpTransit Gotthard railway line.
3/3: Pradella – La Punt: CHF 1.5 million per km – Swissgrid has added a second 380-kV line to the entire 50 km route between Pradella and La Punt. Today, the pylons therefore carry one line on each side. This has a positive impact on emissions, which are lower overall than before.

Cost of underground cabling

1/3: La Bâtiaz – Le Verney CHF 29.1 million per km – The project involves drilling a tunnel with a diameter of around 2.5 metres and a depth of 12 to 20 metres between different groundwater layers over a length of 1.2 kilometres. The special geological conditions at precisely this point on the Rhône plain make this technological masterpiece possible.
2/3: The cost of the construction of partial cabling over a length of 1.3 kilometres with two transitional structures is around CHF 20.4 million. The Beznau – Birr project shows that costs of around 10 to 15 million francs per kilometre are to be expected for partial underground cabling on the Swiss Central Plateau (transitional structures, normal subsoil, crossing under existing infrastructure). This makes the costs for the underground section of the Beznau – Birr extra-high-voltage line about six times higher than for an overhead line over its entire service life.
3/3: Airolo – Mettlen (Gotthard line): CHF 6.0 million per km – Bundled through the mountain: the construction of the second Gotthard Road Tunnel tube offers the opportunity to bundle infrastructure and to lay new extra-high-voltage lines in the service duct which will run under the carriageway.

Basis for decision-making

Large infrastructure takes a long time to build. On average, it can take over 15 years from the start of a project to commissioning – due to lengthy authorisation procedures, frequent objections and court rulings.

The Federal Council reaches a decision for an underground cable or an overhead line during the sectoral plan procedure. An important role is played by a support group set up by the Swiss Federal Office of Energy for each project. It works as follows:

The support group is made up of representatives of several federal offices (e.g. spatial development, environment, transport), the Federal Inspectorate for Heavy Current Installations (ESTI), the Federal Electricity Commission (ElCom), representatives of the affected cantons, an environmental protection organisation and Swissgrid. Each party has one vote. The group makes recommendations to the Federal Council for defining the planning area and planning corridor and deciding on the technology (overhead line or underground cable). Various federal offices introduced a special methodology a few years ago, the «Transmission lines evaluation scheme», to make sure that the best possible solution can be found. It allows the strengths and weaknesses of the variants to be weighed up objectively, comprehensively and systematically. The scheme is based on the four areas of spatial development, technical aspects, environmental protection and cost-effectiveness.

Bundling of infrastructure: Airolo – Mettlen (Gotthard line)

In recent years, Swissgrid has installed underground cable lines with a total length of over 40 kilometres in the transmission system. Swissgrid bundles underground cables with other infrastructure projects wherever possible and whenever it makes sense to do so.

The construction of the second tube of the Gotthard Road Tunnel by 2029 offers Swissgrid a wide range of opportunities. The combination of an extra-high-voltage line with a motorway tunnel is a pioneering project that is the first of its kind in Europe. Swissgrid can gain valuable experience from this technically demanding project. Another plus is that the burden on the Gotthard landscape will be relieved by dismantling 23 kilometres of overhead lines and 70 pylons.

Additional information:

Licensing procedures for electrical installations

Approval process

Transmission Lines sectoral plan


Switchgears and transformers

Substations are among the most important elements in the extra-high-voltage grid because they represent the nodes of the grid. Substations consist of transformers and switchgears. Swissgrid’s extra-high-voltage grid comprises 126 substations housing 148 switchgears and 32 transformers. This means that every substation has a switchgear, but not all substations have a transformer.

Important elements in the transmission grid

The switchgears in the substations connect the extra-high-voltage lines with each other. The operators in the Swissgrid control centres in Aarau and Prilly can disconnect or connect the lines by means of switching operations. By doing so, they can control energy flows, prevent overloads and switch off lines for maintenance work. The substations also have protective systems installed in them. In the event of a fault (e.g. lightning striking a line), they switch off the affected grid sections in a targeted manner.

Illustration of a substation with transformers: the substations are controlled from the control centres in Aarau and Prilly. However, if required, the plant managers can take control of the substations and disconnect elements on site.

Downloads

Contact

Title

Please select a title.

Please enter your first name.

Please enter your last name.

Please enter a valid e-mail address.

Please enter your message.

Please click the checkbox.